Companies

OMV Petrom and Renovatio bring 130 MW of Romanian solar capacity into operation

Solar panels in the photograph supplied with OMV Petrom’s three-park commissioning announcement

Three solar parks developed by OMV Petrom and Renovatio are now supplying Romania’s electricity grid, adding approximately 130 MW of installed capacity at Țăndărei, Bucovăț and Căzănești.

OMV Petrom owns half of the projects, making its attributable capacity around 65 MW. The distinction matters: the 130 MW figure covers the entire partnership, rather than capacity owned solely by OMV Petrom.

The company’s October 28 announcement, cited by Romania Observer, puts development and grid-connection investment at approximately EUR 78 million. The Romanian-language release specifies around EUR 26 million in grants approved through Romania’s recovery plan, PNRR; it does not establish that all grant funds have been disbursed.

Combined annual output is forecast at 0.2 TWh. That is an estimate of future generation, not electricity already produced.

The commissioning brings operational renewable capacity in OMV Petrom’s portfolio, including partnerships, to around 200 MW. The company says another 1,200 MW is under construction and targets more than 2,500 MW operational by 2030.

The immediate development is therefore electricity from commissioned assets; construction volumes and the 2030 goal remain separate future milestones.

Source: OMV Petrom.

Image source: OMV Petrom.

More articles

Do you run a business, promote a personal brand or represent a public institution?

Publish an article, press release, advertorial or announcement, including a job posting, with images and useful links. Your material can be discovered by readers and through search engines.

Publish your material on Romania Observer

Digital services for your business

Discover the solutions we built for promotion, web hosting, communication and managing your business online.