Ooni Koda
  1. Home
  2. /
  3. Newsfeed
  4. /
  5. Retele Electrice Muntenia has finalized the modernization of...

Retele Electrice Muntenia has finalized the modernization of the North Power Station following investments of 70 million lei

April 25, 2024

The modernization of the North Power Station involved the complete consolidation of the building and the replacement of electro energetic equipment, without interrupting the supply to customers. The primary substation serves about 73,000 customers, from the north-central area of Bucharest, many central and local institutions, hospitals and household customers or economic agents.   Retele Electrice Muntenia company (part of the PPC Group, formerly named E-Distributie Muntenia) has finalized the modernization works for the North Power Station, the largest primary substation in the country. The value of the investment is about 70 million lei, from the company's own funds.   The modernization project was particularly complex, as the full consolidation of the building and the replacement of all electro energetic equipment was carried out in stages, with many provisional situations, to carry out the modernization without interrupting the electricity supply to customers.   The primary substation is located in the central area of Bucharest and serves more than 73,000 customers, including central and critical institutions, hospitals and various ministries. The major benefits of the upgrade of North Power Station consist in increasing the security in the supply of existing customers, increasing the flexibility of the high and medium voltage network, as well as the possibility to accommodate increased demands and needs of consumption and regarding the number of customers.   "We continue the process of modernizing and developing the networks to ensure the necessary resilience, flexibility and level of digitization to successfully cope with accelerated electrification and decarbonization processes of energy consumption, for the benefit of the community. The North Power Station upgrade was a large-scale project that required vision and customised engineering and construction solutions. A major challenge was that the works were carried out without interrupting the operation of the primary substation, which meant carrying out the building consolidation and replacing the electro energetic equipment while ensuring the smooth supply to around 73,000 customers. The concern for safety was at an extremely high level, as our colleagues and contractors’ staff worked at height and in the vicinity of the operating installations," said Mihai Peste, general manager Retele Electrice companies.   The North Power Station is equipped with six power transformers of 40 MVA (Mega Volt Amper) each, resulting in an installed power of 240 MVA and a guaranteed power of 160 MVA. The peak load recorded so far was around 127 MVA. This load level represents more than the value of the load in the whole Giurgiu county.   The primary substation is powered by four underground 110 kV power lines, which feature modern dry-insulated cables, and distributes electricity through 66 medium voltage lines, 34 10kV lines and 32 20kV lines. In the primary substation there are installed 64 MV cells (transformer cells, couplings, measurement, internal services and lines) operating at the voltage of 10kV, 76 MT cells (transformer cells, couplings, measurement, internal services and lines) operating at the voltage of 20kV and 11 cells of 110kV (transformer cells, couplers and lines). In the control room which is fully digital, 38 protection, measurement, telecommunications and internal service cabinets are installed, and the total length of the medium voltage cables used in the primary substation’s modernization project is 26.8 km, respectively 61 .5 km for low voltage ones.   The modernization works consisted of replacing all six power transformers with modern, Romanian-made ones, with reduced losses and increased reliability, as well as replacing all 110 kV, 20 kV and 10 kV equipment and installations and secondary circuits. All newly installed equipment is encapsulated (the 110kV ones) or in compact construction (the MV ones). The electrical scheme of the primary substation has been improved by implementing a double busbar solution with longitudinal and transverse couplers, thereby achieving increased flexibility in the 110kV network in Bucharest.   The new transformers with natural cooling have a very low noise level to protect the comfort of nearby residents. In addition, modern switchgear has replaced oil technology, eliminating the risk of explosition and pollution. The new equipment eliminated the need to use about 6,000 liters of mineral oil.   As part of this important investment, the primary substation building, which dates back to 1969, has been completely renovated. As part of the process, brickwork and reinforced concrete totalling more than 11,000 tonnes of materials were demolished in a first phase, then the primary substation building was consolidated in order to eliminate the seismic risk; some 6,000 cubic metres of concrete, more than 700 tonnes of concrete steel, some 75 tonnes of metal components were used. The space was thermally insulated to increase energy efficiency and a lighting system based on LED technology was installed for the same purpose. The work was carried out with the help of in-house teams and contractors who, on average, involved 50 people per month.   The primary substation's interior area of approximately 4,600 square metres is distributed over four floors. Following the installation of the new equipment, which is much more compact than the previous technology, 60% of the available space has been freed up, part of which will be used to build a technology testing and development centre for Retele Electrice companies. The rest of the space can be used for the expansion of electricity distribution istalations, if necessary.   Retele Electrice companies operate networks with a total length of over 133,000 kilometres in three major areas of the country: South Muntenia (including Bucharest), Banat and Dobrogea, covering a third of the local distribution market, and are developing an investment programme to improve service quality, network safety and performance and local implementation of PPC Group environmental standards. The electricity networks operated by the three Retele Electrice companies include 287 primary substations and over 24,000 secondary substations.  

Read in full - click here
One last star to shine: Corinthia Bucharest prepares the final act of its Michelin Dinner Series

Some dinners are eaten. Others are remembered. At Corinthia Grand Hotel du Boulevard, the past few months have unfolded like a quiet culinary opera. One by one, Europe’s most celebrated chefs arrived, took over the kitchen of Boulevard 73 and left behind more than menus; they left stories. Now, on December 4, the curtain falls. […]

HORIZON CITY - The New Residential Anchor of Northern Bucharest

HORIZON CITY, a €130 million residential project, is emerging as one of the most solid and forward-thinking developments in the Pipera area—both through its scale and through the modern direction it sets for the new residential standards in the north. Developed across nearly 23,000 sqm, with 699 apartments and 926 parking spaces, the project brings […]

Romania’s forestry authority Romsilva puts 16,000 Christmas trees up for sale

Romania’s National Forest Administration, or Romsilva, announced that it is putting over 16,000 Christmas trees up for sale over the winter in a press release published on Thursday, November 27. The trees can be purchased directly from the offices of the forestry districts. Prices range between RON 17 (EUR 3.3) for a spruce...

New 14 km segment of Romania’s A7 Moldova highway inaugurated

Lot 3 Pietroasele–Buzău of Romania's A7 highway, also known as the Moldova highway, was inaugurated on Thursday, November 27. The newly inaugurated segment is 13.9 km long. The A7 connects Romania’s historic regions of Muntenia, the southern part of the country, with Moldova, the eastern part. “We are opening another 13 km of the Moldova Motorway […]

Romania’s Sinaia inaugurates alpine coaster for year-round mountain fun

The City Hall of Sinaia, a popular mountain town roughly 120 km north of Bucharest, announced that a new attraction, the alpine coaster on Pârtia Nouă, will officially open on December 1. The installation, located in the ski area near the Sinaia Gondola, features what the authorities say is the longest track of its kind […]

Romania scores first win in group stage of Women’s Handball World Championship

The Romanian national team debuted with a victory in Group A of the Women’s Handball World Championship, organized in the Netherlands and Germany. Romania won 33–24 (13–12) against Croatia in the Ahoy Arena in Rotterdam on Thursday, November 27. The Romanian team dominated the match in the second half, left backer Sorina-Maria Grozav scoring 7 […]